Continue improving nets electric of Camagüey

By:LuciloTejera Díaz

The electric workers in this county carried out in the last four years more than 46 thousand actions of improvement of the nets, in order to optimize the service.

In the 2006 Cuba undertook that work before the decrease of the effectiveness in the transmission and distribution and the high level of losses.

Denis Martínez, technical director of the Electric Basic Organization in the territory, informed that the executed tasks contemplate, among other, the caliber change of having spread, the installation of new posts and the construction of nets. change assaults.

The improvement is expressed in the elimination of about a thousand areas of low voltage and are still some 100 to carry out him the benefit

Also, a superior figure to the 30 thousand 100 housings began to be favored with new electric services. Apart from the investments, maintenance actions were made to the lines.

All these works increased the reliability of the supply from the energy to the clients, the official pointed out.

Of the 2006 at the 2008 the work was intense, and in the current one it diminished for the financial limitations of the country for the adverse impact of the world economic crisis, that which reduced the possibilities of acquisition abroad of resources.